Cross Line Bottleneck Synchronization and Real Time Throughput Balancing

A high speed beverage bottling and packaging plant running 6 canning lines producing 1,500 cans per minute per line across depalletizing, filling, seaming, pasteurization, and case packing.

Run on Yantra · Industrial Operations Console

Parallel lines running out of phase being brought into step
84%plant OEE after rollout
55%fewer conveyor line stoppages
180,000more cans per line daily
The problem2 min read

Micro stoppages lasting 10 to 30 seconds at downstream case packers caused massive conveyor accumulation jams back to the primary filler.

What we did, with Yantra

Optical and Accumulation Sensor Tracking → Micro Stoppage Root Cause Detection → Dynamic Conveyor Speed Modulation → Operator Station Line Flow Displays

The result

Plant Overall Equipment Effectiveness (OEE) increased from 68% to 84%.

The challenge

01

Micro stoppages lasting 10 to 30 seconds at downstream case packers caused massive conveyor accumulation jams back to the primary filler.

02

Line supervisors lacked visibility into instantaneous conveyor buffer levels, leading to line speed mismatches and frequent machine tripping.

03

Daily plant canning output fell 18% below nameplate capacity due to uncoordinated speed transitions and accumulation backlogs.

How our team solved it, with Yantra

  1. 01

    Optical and Accumulation Sensor Tracking

    Yantra monitors can flow rates, photo eye sensor states, and conveyor accumulation buffer percentages in real time.

  2. 02

    Micro Stoppage Root Cause Detection

    Yantra identifies recurring 15 second packaging machine jams and calculates the upstream throughput impact on primary filling units.

  3. 03

    Dynamic Conveyor Speed Modulation

    Yantra adjusts variable frequency drives along conveyor sections to absorb minor downstream delays without stopping the filler.

  4. 04

    Operator Station Line Flow Displays

    Real time bottleneck indicators and buffer capacities appear on overhead LED screens for machine operators.

  5. 05

    Shift Output Loss Analysis

    Yantra gives line managers a shift end loss analysis detailing top downtime contributors and recommended mechanical adjustments.

  6. 06

    Line Manager Sign-Off

    The line manager reviews the recommended adjustments and approves which ones maintenance carries out.

The outcome

Before
  • Micro stoppages lasting 10 to 30 seconds at downstream case packers caused massive conveyor accumulation jams back to the primary filler.
  • Line supervisors lacked visibility into instantaneous conveyor buffer levels, leading to line speed mismatches and frequent machine tripping.
  • Daily plant canning output fell 18% below nameplate capacity due to uncoordinated speed transitions and accumulation backlogs.
After, with Yantra
  • Plant Overall Equipment Effectiveness (OEE) increased from 68% to 84%.
  • Conveyor accumulation line stoppages reduced by 55%, adding 180,000 cans of output per line daily.
  • Micro stoppage diagnostic time reduced from hours of manual video review to instant automated classification.

Delivered for a client; the client name is withheld under NDA. References are available on request.

Capabilities used

Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.

signal ingestionsystem connectorsanomaly detectionroot cause reasoningalert routingin boundary deployment

Run on Yantra

Watch Yantra run, end to end, in a few minutes.

Industrial Operations Console

One role-aware console for equipment health, energy, alarms, and OT security.

See the Yantra accelerator

More from Yantra

Bring us the version of this that you actually have.

Every engagement is fixed in scope and milestone-gated. The scoping conversation starts with your systems, not with a template.