Engineering Change Order Impact Analysis on DFMEA Risk Baselines

A commercial hemodialysis machine manufacturer managing a field fleet of 25,000 clinic dialysis consoles, implementing an engineering change to replace an obsolete blood flow sensor.

Run on Tatvam · Design Risk & DFMEA

One change rippling through a settled risk baseline
3 weeksECO risk impact analysis turnaround time cut
45%design verification testing costs reduced
The problem2 min read

Replacing the flow sensor required evaluating potential new failure modes, firmware algorithm changes, and fluid dynamics impacts.

What we did, with Tatvam

ECO Impact Scanning → Baseline Branching → Re-Evaluation Alerts → Test Scope Optimization

The result

ECO risk impact analysis turnaround time cut from 3 weeks to 2 hours.

The challenge

01

Replacing the flow sensor required evaluating potential new failure modes, firmware algorithm changes, and fluid dynamics impacts.

02

Engineers lacked an automated way to determine which sections of the 3,000 row DFMEA were touched by the component revision.

03

An overlooked sensor sampling frequency mismatch caused intermittent air bubble false alarms in clinical trials after ECO release.

How our team solved it, with Tatvam

  1. 01

    ECO Impact Scanning

    Tatvam scans the full system risk model against proposed ECO component revisions and highlights every affected failure mode.

  2. 02

    Baseline Branching

    The active DFMEA baseline is branched into a sandbox so engineers can model new risk scores without altering production records.

  3. 03

    Re-Evaluation Alerts

    Fluidics, electronics, and software engineers are asked to review the specific affected hazard lines before ECO approval.

  4. 04

    Test Scope Optimization

    Tatvam pinpoints the subset of verification protocols that must be re-run, avoiding full system retesting.

  5. 05

    Change Board Sign-Off

    Verified risk updates merge into the master DFMEA baseline only after formal change board approval.

The outcome

Before
  • Replacing the flow sensor required evaluating potential new failure modes, firmware algorithm changes, and fluid dynamics impacts.
  • Engineers lacked an automated way to determine which sections of the 3,000 row DFMEA were touched by the component revision.
  • An overlooked sensor sampling frequency mismatch caused intermittent air bubble false alarms in clinical trials after ECO release.
After, with Tatvam
  • ECO risk impact analysis turnaround time cut from 3 weeks to 2 hours.
  • Design verification testing costs reduced by 45% by targeting only affected risk control pathways.
  • Zero post release clinical false alarms or unintended design side effects.

Delivered for a client; the client name is withheld under NDA. References are available on request.

Capabilities used

Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.

document intelligencerisk scoringgenerative designevidence audit trailpolicy compliancehuman approval

Run on Tatvam

Watch Tatvam run, end to end, in a few minutes.

Design Risk & DFMEA

The whole failure-mode workflow in one control room, auditable end to end.