Setup Grouping and Changeover Minimization in Contract Electronics
A high-mix Contract Electronics Manufacturer (CEM) operating 12 Surface Mount Technology (SMT) lines producing PCBA boards for automotive and industrial IoT clients.
Run on Niyojan · Production Planning

Frequent order changeovers between custom customer PCBA jobs consumed 35% of total line operating hours in setup downtime (re-reeling component feeders, changing solder stencils).
BOM Component Similarity Grouping → Optimal Setup Sequence Generation → Stencil and Feeder Changeover Minimization → Customer SLA Compliance Checking
Machine changeover setup downtime reduced by 58%, freeing 14 hours of line capacity per SMT line each week.
The challenge
Frequent order changeovers between custom customer PCBA jobs consumed 35% of total line operating hours in setup downtime (re-reeling component feeders, changing solder stencils).
Planners scheduled orders strictly by customer priority date, causing excessive machine changeovers between jobs sharing identical component reels.
SMT machine line efficiency (OEE) dropped to 52% due to setup downtime.
How our team solved it, with Niyojan
- 01
BOM Component Similarity Grouping
Niyojan analyzes active work order BOMs, identifying jobs that share high percentages of identical SMT component reels.
- 02
Optimal Setup Sequence Generation
Niyojan sequences jobs to group shared component reels together, minimizing feeder re-reeling downtime between runs.
- 03
Stencil and Feeder Changeover Minimization
Niyojan calculates changeover time penalties for alternative sequences and selects the one that maximizes net machine run-time.
- 04
Customer SLA Compliance Checking
Every proposed sequence is checked against customer delivery lead times and contract SLA windows.
- 05
Planner Approval and Instructions
The production planner approves the sequence, and Niyojan sends detailed feeder setup instructions to SMT line operators.
The outcome
- Frequent order changeovers between custom customer PCBA jobs consumed 35% of total line operating hours in setup downtime (re-reeling component feeders, changing solder stencils).
- Planners scheduled orders strictly by customer priority date, causing excessive machine changeovers between jobs sharing identical component reels.
- SMT machine line efficiency (OEE) dropped to 52% due to setup downtime.
- Machine changeover setup downtime reduced by 58%, freeing 14 hours of line capacity per SMT line each week.
- SMT line Overall Equipment Effectiveness (OEE) increased from 52% to 74%.
- Increased plant throughput by 22% without purchasing additional capital machinery.
Delivered for a client; the client name is withheld under NDA. References are available on request.
Capabilities used
Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.
Run on Niyojan
Watch Niyojan run, end to end, in a few minutes.

Multi-plant production planning at enterprise scale.
See the Niyojan acceleratorMore from Niyojan

Global 60+ Plant Capacity Balancing and Workload Re-Allocation
A multinational industrial equipment manufacturer operating 60+ production facilities across 4 continents, producing custom hydraulic pumps, valves, and heavy gearboxes.
Read the use case
Dynamic Resequencing Following Unplanned Primary Line Failure
A high-volume automotive stamping and welding plant producing body panels for 3 concurrent vehicle assembly platforms.
Read the use case
Order SLA Protection and Overtime Minimization During Demand Spikes
A commercial HVAC equipment manufacturer producing custom rooftop air handling units with high seasonal demand surges during pre-summer months.
Read the use caseBring us the version of this that you actually have.
Every engagement is fixed in scope and milestone-gated. The scoping conversation starts with your systems, not with a template.