Harmonizing EBOM to MBOM Discrepancies During Electric Vehicle Ramp
An Electric Vehicle (EV) original equipment manufacturer ramping up a new dual motor SUV platform across two high volume vehicle assembly plants.
Run on Sama · BOM Synchronization

Frequent Engineering BOM (EBOM) updates released by R&D; (such as battery busbar revisions and harness routing updates) were out of sync with plant Manufacturing BOMs (MBOMs).
Unified BOM Dashboard → Discrepancy Detection → Part Dependency Trees → ECO Impact Analysis
ECO reconciliation and MBOM update cycle time cut from 3 weeks to under 4 hours.
The challenge
Frequent Engineering BOM (EBOM) updates released by R&D; (such as battery busbar revisions and harness routing updates) were out of sync with plant Manufacturing BOMs (MBOMs).
Plant manufacturing engineers relied on weekly spreadsheet reconciliations, leading to assembly line part shortages and line stoppage.
Engineering Change Orders (ECOs) took up to 3 weeks to manually reconcile across plant MBOMs, resulting in $1.8M in obsolete component write offs.
How our team solved it, with Sama
- 01
Unified BOM Dashboard
Sama brings CAD-derived EBOMs and plant-specific MBOMs into a single real time synchronization view.
- 02
Discrepancy Detection
Sama highlights part number mismatches, quantity deltas, and revision discrepancies between engineering and manufacturing.
- 03
Part Dependency Trees
Interactive dependency trees show how changes to battery modules ripple into structural brackets and wiring harnesses.
- 04
ECO Impact Analysis
Line item revision deltas are computed, and manufacturing engineers are alerted to pending engineering change releases.
- 05
Engineer-Approved MBOM Dispatch
The plant manufacturing engineer approves each change, and Sama pushes it to plant ERP and MES systems without manual re-entry.
The outcome
- Frequent Engineering BOM (EBOM) updates released by R&D; (such as battery busbar revisions and harness routing updates) were out of sync with plant Manufacturing BOMs (MBOMs).
- Plant manufacturing engineers relied on weekly spreadsheet reconciliations, leading to assembly line part shortages and line stoppage.
- Engineering Change Orders (ECOs) took up to 3 weeks to manually reconcile across plant MBOMs, resulting in $1.8M in obsolete component write offs.
- ECO reconciliation and MBOM update cycle time cut from 3 weeks to under 4 hours.
- BOM mismatch related assembly line stoppages reduced by 94% during platform launch.
- Scrap and obsolete component inventory write offs reduced by $1.4M.
Delivered for a client; the client name is withheld under NDA. References are available on request.
Capabilities used
Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.
Run on Sama
Watch Sama run, end to end, in a few minutes.

Engineering, manufacturing, service, and software BOMs kept in step as designs move.
See the Sama acceleratorMore from Sama

Aligning Hardware EBOM and Embedded Firmware Software BOM
A smart automotive Tier 1 supplier producing Advanced Driver Assistance System (ADAS) domain controllers integrating radar sensors, cameras, and microcontrollers.
Read the use case
Field Service BOM Alignment for Warranty and Aftermarket Operations
A commercial bus and truck manufacturer with a global dealer network managing 150,000 active fleet vehicles across 25 international markets.
Read the use case
Multi Factory Plant Specific MBOM Reconciliation in Automotive Assembly
A global automotive conglomerate producing a high volume crossover vehicle across 4 assembly plants in North America, Europe, and Asia.
Read the use caseBring us the version of this that you actually have.
Every engagement is fixed in scope and milestone-gated. The scoping conversation starts with your systems, not with a template.