Catastrophic Factory Disruption and Multi Site Work Order Resequencing
A major industrial valve and actuator manufacturer with 5 plants, experiencing a major structural fire at Plant 2 that disabled the main heat treatment and machining bay for 60 days.
Run on Sankalp · Disruption Replanning

Plant 2 had 320 open customer work orders worth $42M in progress, representing 40% of the company quarterly revenue commitments.
Facility Lockout and WIP Audit → Cross Plant Capability Matching → Work Order Splitting and Redistribution → Operations Director Approval
91% of stranded production orders successfully completed and delivered within revised customer SLA windows.
The challenge
Plant 2 had 320 open customer work orders worth $42M in progress, representing 40% of the company quarterly revenue commitments.
Operations teams were overwhelmed, spending 5 days manually sorting through paper travelers to identify stranded job stages.
Competitors prepared to capture market share if customer orders were canceled or delayed by months.
How our team solved it, with Sankalp
- 01
Facility Lockout and WIP Audit
Sankalp registers the full facility outage and audits the status and completion percentage of all 320 active work orders.
- 02
Cross Plant Capability Matching
Sankalp scans open machine capacity and tooling compatibility across the remaining 4 operational plants in real time.
- 03
Work Order Splitting and Redistribution
Sankalp splits multi stage jobs, routing unfinished rough castings to Plant 3 for heat treatment and Plant 4 for 5 axis machining.
- 04
Operations Director Approval
The operations director reviews the proposed redistribution and approves it before any work moves between plants.
- 05
Expedited Material Logistics
Sankalp coordinates emergency inter facility trucking to move semi finished WIP inventory between plants.
- 06
Customer SLA Communication
Sankalp generates updated delivery commit dates for sales teams to share with major industrial clients.
The outcome
- Plant 2 had 320 open customer work orders worth $42M in progress, representing 40% of the company quarterly revenue commitments.
- Operations teams were overwhelmed, spending 5 days manually sorting through paper travelers to identify stranded job stages.
- Competitors prepared to capture market share if customer orders were canceled or delayed by months.
- 91% of stranded production orders successfully completed and delivered within revised customer SLA windows.
- Complete multi plant disaster recovery replanning executed in 4 hours rather than weeks of manual coordination.
- Retained 100% of top tier customer accounts despite a catastrophic 60 day single plant outage.
Delivered for a client; the client name is withheld under NDA. References are available on request.
Capabilities used
Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.
Run on Sankalp
Watch Sankalp run, end to end, in a few minutes.

When freight, tariffs, or material prices move, arrive with options, not alerts.
See the Sankalp acceleratorMore from Sankalp

Raw Material Price Shock Absorption and Margin Preserving Replanning
A major structural steel and heavy pressure vessel manufacturer consuming 45,000 metric tons of specialized alloy plate and forged fittings annually.
Read the use case
Global Freight Disruption and Intermodal Logistics Rerouting
A global power equipment manufacturer shipping heavy transformers and turbine housings via international maritime, rail, and heavy haul trucking routes.
Read the use case
Geopolitical Trade Tariff and Supply Chain Embargo Mitigation
An international defense and aerospace subsystem manufacturer sourcing precision machined forgings and optical components across multiple global jurisdictions.
Read the use caseBring us the version of this that you actually have.
Every engagement is fixed in scope and milestone-gated. The scoping conversation starts with your systems, not with a template.